Commissioning Agent Costs

Total building commissioning costs for commissioning agent services can range from 0.5% to 1.5% of total construction costs (according to U.S. Department of Energy’s Rebuild America Program, written by the Portland Energy Conservation, Inc. (PECI)).  The National Association of State Facilities Administrators (NASFA) recommends budgeting 1.25 to 2.25% of the total construction costs for total building commissioning agent services. GSA’s commissioning practice is expected to cost approximately 0.5% of the construction budget for federal buildings and border stations. More complex projects such as courthouses could run 0.8 - 1% of the construction budget, and even more complex facilities such as laboratories can exceed 1%.  Factors influencing commissioning costs include facility type, phasing 24/7 operations, the depth and breadth of commissioning services, the level of commissioning desired, and the systems and assemblies chosen to be commissioned.

Last Reviewed 2015-12-22