Transition Timeline

As of August 15, 2016

Agencies should meet the following critical milestones to ensure services are transitioned before their current contracts expire:

  • Agencies confirm the Transition Inventory (TI) – October 2016
  • Agencies develop Agency Transition Plans (ATPs); Transition Sponsor delivers ATP to GSA ITS – October 2016
  • Agencies release solicitations for Fair Opportunity (FO) selection of EIS contractors – May 2017
  • Agencies award task orders for EIS services – March 2018
  • Agencies achieve 50 percent (50%) transition of services – March 2019
  • Agencies achieve 100 percent (100%) transition of services – March 2020 (when Networx Universal expires)

We've provided an illustrative timeline below:

Illustration of the EIS Transition Timeline