San Ysidro LPOE Funding
The currently projected cost of the project is approximately $741 million.
Project funding was requested in phases during each fiscal year, as follows:
Fiscal Year | Funding Amount | Type of Funding |
---|---|---|
FY 04 | $34.2 million | Site and Design |
FY 08 | $37.7 million | Site and Design |
FY 08 | $161.4 million | Construction (Phase 1 Partial) |
FY 09 | $58.9 million | Construction (Phase 1 Completion) |
FY 11 | $6.2 million | Construction (Phase 1C) |
FY 14 | $226 million | Site, Design and Construction (Phase 3) |
FY 15 | $216.8 million | Design and Construction (Phase 2) |