Greenville U.S. Courthouse

Greenville Federal Courthouse Rendering

On December 18, 2015, the 114th United States Congress passed the Consolidated Appropriations Act of 2016 which included funding for a new federal courthouse in Greenville, MS. The General Services Administration (GSA) engaged with the U.S. Courts and Department of Justice to determine space requirements and establish the project budget. On November 15, 2016, Congress authorized GSA to proceed with the expenditure of $40.1 million in order to acquire a site, develop a design, and construct the new federal courthouse.

Current Status (August 2021)

The project is in the Construction Documents phase of design.

Latest Updates

The concept design for the facility has been approved and the Architect of Record is now developing the design to support construction beginning in Fall 2021.

GSA awarded the Art in Architecture commission to Mississippi-based artist, Critz Campbell.

Additional information may be found by following the links under 'News Releases' below.

Next Milestone

The construction groundbreaking ceremony is scheduled to occur in Fall 2021.

Project Details

  • Total Authorized Funding: $40,102,000 (site acquisition, design, construction, and related expenses)
  • Project Delivery Method: Design-Bid-Build
  • Architect: Duvall Decker Architects (Co-Lead Designers: Roy Decker - Duvall Decker & Steve Dumez - Eskew+Dumez+Ripple)
  • General Contractor: TBD
  • Anticipated Milestones:
    • Design Start: Spring 2018
    • Design Complete: Summer 2021
    • Construction Start: Fall 2021
    • Construction Complete: Summer 2023
  • Awarded Contracts:
    • Duvall Decker Architects (Architect of Record - February 2018)
    • APSI Construction Management (Construction Manager as Advisor - June 2018)
    • Critz Campbell (Art in Architecture - April 2020)

Media Inquiries

Tina Jaegerman
GSA Public Affairs Officer
R7media.inquiries@gsa.gov

News Releases

Last Reviewed: 2021-08-03