Project Timeline

2014

August - The government issued a Request for Information (RFI) to obtain responses from real estate developers, institutional landholders, construction entities, joint ventures, and other members of the development community that are potentially interested in acquiring portions of the property through an exchange process. The government used the information provided for planning purposes and to make strategic decisions regarding the future use of the property. More details>

September - An Industry Day briefing and tour intended solely for potential respondents to the RFI was held on Saturday, September 20, 2014 from 9:00 a.m. to 1:00 p.m. at the Property. More details>

2015

May - In May 2015, GSA awarded a call under an existing Blanket Purchase Agreement (BPA) for the completion of a Program of Requirements (POR). The POR will document functions and needs of a new facility for the Volpe Center and will be an integral part of any future solicitation. The Scope of Work contract was awarded in September 2015.

July - On July 16, 2015, GSA issued a Request for Qualifications (RFQ) for the Exchange Transaction for Volpe Center. More details>

2016

June - Request for Proposals (RFP) issued on June 15, 2016

September - RFP responses due on September 8, 2016

November - On November 15, the government announced the initial selection of Massachusetts Institute of Technology (MIT) as the Exchange Partner for the Volpe Project.
 

 