Completed Capital Projects

Completed Capital Projects

GSA strives to deliver projects On-Schedule and On-Budget to help mitigate costly overruns and schedule delays. By keeping scope, schedule, and costs aligned, project teams can deliver projects that enable Federal Agencies achieve their mission at best value for the American Taxpayer. The information below identifies completed capital projects schedule and budget performance.

Completed Major Construction Projects FY20 [PDF - 12 KB]

State City Project Actual Duration (Years) Budget Variance To Final Baseline
PR San Juan FBI Field Office Consolidation 3.74 5%
VA Winchester FBI Central Records Complex 2.71 2%
PA Pittsburgh Weis U.S. Courthouse SSA Consolidation 1.31 5%
FL Pensacola District Courthouse Modernization 2.58 1%
MI Detroit Theodore Levin U.S. Courthouse 4.76 7%
OH Cincinnati John Weld Peck Federal Building Backfill 2.10 5%
WI Milwaukee Federal Building & U.S. Courthouse Facade Restoration 2.17 1%
TX Austin JJ Pickle Federal Building R&A 2.74 3%
ND Pembina APHIS Building 2.12 -3%
CO Lakewood Denver Federal Center Emergency Roof Replacement 1.56 0%
CA San Diego San Ysidro U.S. Border Station (Phase 3) 3.70 6%
DC Washington Robert Weaver 2.21 11%
DC Washington 1800 F Elevators 1.98 0%