GSA strives to deliver projects On-Schedule and On-Budget to help mitigate costly overruns and schedule delays. By keeping scope, schedule, and costs aligned, project teams can deliver projects that enable Federal Agencies achieve their mission at best value for the American Taxpayer. The information below identifies completed capital projects schedule and budget performance.

Completed Major Construction Projects FY21 [PDF - 53 KB]

State City Project Actual Duration (Years) Budget Variance To Final Baseline
MA Boston McCormack Federal Building Exterior Masonry Repairs 1.46 8%
NY Manhattan Javits Federal Building 3.44 13%
NY Manhattan Weiss Federal Building Elevator Modernization 2.78 0%
PR San Juan Degetau Federal Building Hurricane 2.12 37%
GA Savannah New Court House Annex 3.62 1%
NC Charlotte Jonas Courthouse New Annex 3.25 6%
SC Greenville New Courthouse 3.81 6%
DC Washington Mary Switzer Federal Building Consolidation & Conference Center 2.89 3%