Implement the new economic price adjustment clause
What’s new with EPA clause GSAR 552.216-90 Economic Price Adjustment (GSAR Deviation) (Sept 2026) Alternate I (Sept 2026)
Effective with MAS Solicitation Refresh 34, clause 552.216-90 replaces clause 552.238-120. While fixed annual price escalation is no longer classified as an EPA mechanism, offerors retain the option to submit fixed outyear pricing featuring an agreed-upon annual escalation implemented on the anniversary of the contract award. Additionally, EPAs covering unexpected and significant market shifts remain available under applicable MAS contracts.
What stays the same
- Existing EPA Methods using a Market Index or Established Pricing: The implementation of the new clause does not require contractors to establish a new method if one has already been agreed upon and incorporated. Where the mechanism still exists under SCP-FSS-001, the existing EPA method automatically transitions upon acceptance of MAS Solicitation Refresh 34 (no modification required).
- Adjustments Based on Unforeseeable Significant Market Changes: As with prior guidance, this mechanism continues to be incorporated automatically into all MAS contracts SCP-FSS-001.
What Changes
- Fixed escalation on the anniversary date of contract award is a pricing arrangement but not an EPA.
Incorporate the method and mechanism for Offers
Submission before MAS Solicitation Refresh 34
Your assigned contracting officer or contract specialist — your CO or CS — will prompt you to accept the most current Refresh and update your documentation, if needed.
Submission after MAS Solicitation Refresh 34
The solicitation will contain the new EPA clause. Provide the required info in the Pricing Terms attachment before submitting your offer.
Existing contracts:
Contracts with existing EPA Methods that include a Fixed Annual Escalation Mechanism:
Under Wave 4 of the Revolutionary GSAR Overhaul (RGO 2026-01), effective November 30, 2026, a fixed annual escalation is no longer considered an Economic Price Adjustment (EPA) mechanism. However, offerors may propose fixed annual escalations as a pricing arrangement, subject to solicitation requirements and contracting officer approval.
Existing contracts with fixed annual escalations tied to the contract award anniversary date will retain their established pricing arrangements under the agreed-upon terms. These escalations will not be classified as EPAs, and no contract modification is required.
Contracts with existing EPA Methods including adjustments based on unforeseeable significant changes in market conditions:
This mechanism is incorporated automatically into all MAS contracts (reference SCP-FSS-001).
For contracts where the revise terms and conditions modification was not completed after MAS Solicitation Refresh 29 (incorporating the previous EPA clause 552.238-120 to incorporate a method (including mechanism and any limitations), a modification to incorporate an EPA method may be required.